ECC21578806 11 26 - Biodiversity-related expenditure secured as a Local Planning Authority

  • Received date31/10/2026
  • Business area Districts and Boroughs
  • OutcomeInformation not held
  • SourceMember of the Public

Request summary

Environmental Information Regulations Request

Reference:     ECC21578806 11 26
Response:    18 November 2026

I can confirm that Essex County Council does not hold this information.

A breakdown of environment- and biodiversity-related expenditure secured in your capacity as a Local Planning Authority through:

o    s106 agreements, including relating to:
    planning conditions;
    nutrient neutrality;
    both if administered by yourself or a private body;
    any other non-Biodiversity Net Gain (BNG) instruments;
o    Community Infrastructure Levies (CILs);
o    on-site BNG delivery.

Specifically, this relates to predicted or actual (for the latter, if known) developer expenditure, secured through these instruments, for interventions relating to those developments (as at the time of agreement signing). The time period is either, depending on your data practices: by calendar year, 2023, 2024, 2025; or by financial year, 2023/24; 2024/25; 2025/26.

To define environment- and biodiversity-related expenditure, the primary purpose of such expenditure must be for the natural environment and for biodiversity. Other purposes must be incidental. For example, expenditure secured for the delivery of sports amenity ground through a CIL, or expenditure secured for the delivery of a public park through a s106 agreement, would not be eligible. But expenditure relating to SAC/SPA mitigation would most certainly be eligible.

Please group interventions into the following: area-based interventions, i.e. a given area of a habitat type; and non-area-based interventions.

For area-based interventions, you can use the below list to cross-reference and categorise for your ease. Please list the area delivered for each intervention (in hectares, or km if distance is the relevant measure), as well as its cost. Interventions, though, may or may not be categorisable therewith, and the below list should not be considered exhaustive.

1.    Grassland;
2.    Heathland and Shrub;
3.    Individual Trees;
4.    Lakes;
5.    Wetland;
6.    Woodland and Forest;
7.    Coastal Lagoons;
8.    Coastal Saltmarsh;
9.    Rivers and Streams.

For non-area-based interventions, you can use the below list to cross-reference and categorise for your ease. Please list a relevant quantity for each intervention, as well as its cost. Interventions, though, may or may not be categorisable therewith, and the below list should not be considered exhaustive.

1.    Artificial Refugia;
2.    Artificial roosts within Developments;
3.    Avoid Hedgerow Illumination;
4.    Avoid Illumination of Commuting Routes;
5.    Avoid illumination of roosts;
6.    Barn Owl Box;
7.    Bat Boxes;
8.    Bird Boxes;
9.    Brash Pile Creation;
10.    Building material phased removal;
11.    Change timing vegetation clearance;
12.    Clear habitat outside breeding/hibernation season;
13.    Compost Heap Creation;
14.    Cover Trenches;
15.    Deadwood Removal Outside Breeding Season;
16.    Deadwood Retention;
17.    Demolition outside hibernation;
18.    Destructive Search;
19.    Dormouse Boxes;
20.    Exclude Bats During Works;
21.    Fencing Construction Zone Exclusion;
22.    Hedgehog Nesting Boxes;
23.    Hedgerow Creation;
24.    Hedgerow Enhancement;
25.    Heras fencing exclusion construction zone;
26.    Hibernaculum Creation;
27.    Log Pile Refugia;
28.    Low Intensity Lighting;
29.    Low UV Lighting;
30.    Nest Translocation;
31.    Offsite Compensation;
32.    Phased Vegetation Clearance;
33.    Planting berry/fruit-bearing trees and shrubs;
34.    Planting of Wildflower Strips/Meadows;
35.    Planting Wildflower Mixes;
36.    Pond Creation;
37.    Pond Restoration;
38.    Relocation if encountered;
39.    Reptile translocation off-site;
40.    Reptile translocation on-site;
41.    Restrict works daylight hours badgers;
42.    Sensitive Fencing;
43.    Sensitive fencing badgers;
44.    Soft Felling;
45.    Soft Strip Demolition;
46.    Time Works Outside Breeding Season;
47.    Topsoil Strip;
48.    Translocation;
49.    Trench Escape Provision;
50.    Tunnels/Culverts;
51.    Warm Light LED.

In addition to categorising according to this second list where possible, please make clear what the purpose of each intervention was. For example, if the intervention was the creation of a hedgerow, please make clear whether this was for the benefit of one or multiple within the following taxonomy:

1.    Badgers;
2.    Bats;
3.    Birds;
4.    Dormice;
5.    Great Crested Newts;
6.    Hedgehogs;
7.    Invertebrates;
8.    Reptiles.

If a number of different interventions are set out by the instrument in question and their respective costs are not broken down, please simply provide the aggregate figure along with the listed intervention(s). Additionally, please provide the term length of the instrument (e.g. the term of a s106 agreement) where relevant, with its start date listed too. Please also provide the planning application/reference number of each development that the instrument is linked to.

While I appreciate it is not required to do so, it would be desirable if the data could be structured as follows:

o    Column 1: intervention type [area-based, non-area-based];
o    Column 2: [if area-based] habitat type;
o    Column 3: [if area-based] area;
o    Column 4: [if non-area-based] intervention type;
o    Column 5: [if non-area-based] intervention purpose;
o    Column 6: [if non-area-based] intervention quantity (however measured);
o    Column 7: projected or actual cost of intervention;
o    Column 8: date of intervention [the date of the relevant instrument agreement];
o    Column 9: instrument type [e.g. s106, CIL, BNG];
o    Column 10: instrument sub-type [e.g. if instrument is s106, then: planning condition; nutrient neutrality; etc.];
o    Column 11: instrument term length (where relevant);
o    Column 12: planning application/reference number;
o    Column 13: location [postcode district or grid reference].

Please do not include any instances which would involve double-counting by bodies like Natural England, the Planning Inspectorate, or highway authorities.

If the time taken to ascertain this information is considered manifestly unreasonable, please work backwards temporally: so begin with 2025 or 2025/26. Please also consider the requirement to consider partial disclosure in all instances (e.g. redact information considered commercially confidential rather than refusing the request as a whole).

I look forward to hearing from you. Please feel free to get in touch should any clarifications be necessary.

I can confirm that Essex County Council does not hold this information. Your request should be directed to City, District and Borough Councils who may be able to provide you with the information. Please see our webpages which should help you further. 
 
Request information about the Council | Essex County Council 
Contact your local council | Essex County Council 

 

Your Right to Know
Democracy and Transparency
Essex County Council
Telephone: 033301 38989
Email: YourRight.ToKnow@essex.gov.uk | www.essex.gov.uk

 

Response

Most computers will open PDF documents automatically, but you may need to download Adobe Reader first.